Breakpad/Status Meetings/2017-01-11: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
mNo edit summary
Line 66: Line 66:


* Will is taking January 26th and 27th off.
* Will is taking January 26th and 27th off.
* Matt is taking January 20th off.


== Links ==
== Links ==

Revision as of 18:08, 11 January 2017

« previous meetingindexnext week » create?

Meeting Info

Breakpad status meetings occur on Wed at 10:00am Pacific Time.

Conference numbers:

   Vidyo: Stability 
   650-903-0800 x92 conf 98200#
   800-707-2533 (pin 369) conf 98200# 

IRC backchannel: #breakpad
Mountain View: Dancing Baby (3rd floor)

Operations Updates

  • what's the status of the infrastructure?
  • There was an unsuccessful prod deploy
    • there was a successful stage deploy
    • prod deploy didn't go
      • wasn't able to find the proper AMI
      • flaky script tagging the API
      • script is flaky because it pipes multiple, complicated, awk-type things together
  • script coming this week to do CI/CD for stage
  • antennae system test

Project Updates

Deployment Triage

PR Triage


Major Projects

Splitting out collector (Antenna)

  • (will) running crashes through antenna and socorro-collector and comparing output. found one bug and fixed it.
  • (will, adrian, lonnen, mbrandt) various discussions on extracting things from antenna into a common library we can all use. at first, the thinking was to split out a test lib, but now seems prudent to make the scope more expansive. Will is going to prototype a library and mull over ease-of-maintenance and convenience.
  • (mbrandt) working on load tests.
  • (miles) working on -stage environment and getting system tests to work in -dev.

Deprecation rampage

e2e tests

  • (will) closed the phantomjs support PR and abandoned this solution for now
  • (will) looking at Selenium docker containers to solve Peter's open/close issue
  • (adrian) reviewed and landed API tests

Processor rewrite

Signature generation hacking

Other Business

  • [mbrandt] Antenna load tests are in a ready state. We'll need to schedule some of rpapa's time when we are ready to execute them and run our sizing experiments.

Travel, etc

  • Will is taking January 26th and 27th off.
  • Matt is taking January 20th off.

Links